Fitness center and locker rooms — downtown Columbus office building

Projects / MIN-2026-0318 — Commercial Interiors / TI

Fitness center and locker rooms — downtown Columbus office building

Amenity buildout in an occupied downtown office tower — exposed overhead sprayed dryfall, accent walls in finish paint, and locker rooms coated to a washable standard.

Fitness center and locker rooms — downtown Columbus office building
3
Coating systems
0
Tenant hours lost
0
Overspray claims
100%
First-walk pass

Narrative


The floor stayed open above and below us. Work was sequenced around building occupancy and freight-elevator windows so tenants never shared a corridor with a spray operation.

Overhead deck, ductwork, conduit, and hangers were sprayed with dryfall to read as one uniform plane, with containment set so nothing migrated to finished floors or installed equipment.

Hollow-metal frames, guards, and misc. metals were finished direct-to-metal. Accent banding — the navy column and the orange cardio wall — was coordinated to the tenant's finish schedule, and locker rooms were coated to a scrubbable standard for daily wet cleaning.

Sequence


  1. 01Protect finished floors, equipment, and glazing; set containment
  2. 02Spray exposed deck, duct, conduit, and hangers with dryfall
  3. 03Gyp prep and Level 4 touch-up at walls and soffits
  4. 04DTM hollow-metal frames, guards, and misc. metals
  5. 05Finish coats at walls and accent bands
  6. 06Locker rooms to washable finish; punch and turnover

Field record


Cardio equipment run along a finished orange accent wall with sprayed overhead structure
Locker room vanity and lockers finished to a washable standard