Projects / MIN-2024-0827

Sector — Healthcare

Regional hospital — OR floor and cove

Eight surgical suites returned to service Monday morning, every weekend, for six consecutive weekends.

Regional hospital — OR floor and cove
8
Surgical suites
6
Weekend phases
10⁶Ω
ESD resistance
7yr
System warranty

Narrative


Anti-static performance verified per ANSI/ESD S20.20. Integral cove base eliminated cleaning seams.

Air quality and noise monitored continuously to meet ICRA Class IV containment.

Sequence


  1. 01ICRA Class IV containment installed Friday evening
  2. 02Diamond-grind to CSP 3
  3. 03Conductive primer with copper grid
  4. 04ESD epoxy body and topcoat
  5. 05Resistance verification per ANSI/ESD S20.20

§ 05 — Engage

Mobilize a crew to your facility.

Scope walks within 72 hours of inquiry. Phased schedules built around continuous operations.

Request a scope walk