Projects / MIN-2025-0307
Sector — Higher Ed
University stadium — traffic deck membrane
Replaced failing pedestrian deck membrane between concourses during the off-season window.

- 62k sf
- Deck area
- 4wk
- Total schedule
- 10yr
- Warranty
- 0
- Schedule overrun
Narrative
Worked between final regular-season game and spring practice. Fast-cure aliphatic topcoat allowed phased return to service.
Sequence
- 01Survey existing membrane, map debonded areas
- 02Selective demo and substrate repair
- 03Primer, base coat, intermediate, topcoat
- 04Aggregate broadcast in pedestrian zones