Projects / MIN-2025-0307

Sector — Higher Ed

University stadium — traffic deck membrane

Replaced failing pedestrian deck membrane between concourses during the off-season window.

University stadium — traffic deck membrane
62k sf
Deck area
4wk
Total schedule
10yr
Warranty
0
Schedule overrun

Narrative


Worked between final regular-season game and spring practice. Fast-cure aliphatic topcoat allowed phased return to service.

Sequence


  1. 01Survey existing membrane, map debonded areas
  2. 02Selective demo and substrate repair
  3. 03Primer, base coat, intermediate, topcoat
  4. 04Aggregate broadcast in pedestrian zones